Reconstruction of St. Theresa's Catholic Mission in Telegraph Creek
Assessing the sites (May 21, 2019)
Leveling the sites (End of May 2019)
Ground breaking day (June 2019)
Utilities (June 2019)
Preparing the church site for concrete (Mid-July 2019)
Preparing the house site for concrete (Mid-July 2019)
Pouring concrete for the church (July 30 - 31, 2019)
Pouring concrete for the house (July 30 - 31, 2019)
Bishop Vila on a recent visit to the site - Reviewing the plans (July 28, 2019)
Building the walls for the house (First week in August 2019)
Church walls going up (First week in August 2019)
Bishop Vila visits the construction site (August 17, 2019)
Roofs going up (September 4, 2019)
Church wrap installation (September 21, 2019)
House and church wrap installation (September 21 & 30, 2019)
Preparing the logs for the church entrance (September 30, 2019)
Windows in the church (October 4, 2019)
Installing the log entry way of the church (October 5, 2019)
Windows and doors on the house (October 10, 2019)
More progress on the church (October 24, 2019)
Church roof and bell tower (November 5, 2019)
Installing the septic systems (November 7, 2019)
The weather-clad church is ready for the first big snowfall (November 8, 2019)
Installing insulation in the Church and House (November 29, 2019)
New drywall in the Church (December 12, 2019)
Drywalling in the Church continues (December 16, 2019)
Progress on the church siding (April 6, 2020)
Installation of the church windows is completed (April 15, 2020)
Church siding is completed (April 17, 2020)
First coat of paint in the house (April 30, 2020)
Finishing in the main part of the church progresses (May 20, 2020)
Soffits, siding and trim on the house are complete (May 21, 2020)
Trim in the church is on and the flooring is next (June 2, 2020)
Storage Shed (June 2020)
Roofing on the house carport and storage shed (June 12, 2020)
Installation of the flooring in the church (June 12, 2020)
Church with carpeted sanctuary (July 13, 2020)
Installing flooring and cabinets in the house (July 14, 2020)
Furnishings in the church (August 3, 2020)
Bishop Vila's visit to St. Theresa's (August 22, 2020)
The new altar and lectern specially made for, and donated to, St. Theresa's have arrived in the Diocese from Toronto (August 26, 2020)
The Church complete with the Altar (September 14, 2020)
Move-in day at the rectory (September 14, 2020)
Landscaping begins (September 23, 2020)
Church lighting (December 8, 2020)
New Crucifix installed and Christmas decorations (December 23, 2020)
St. Theresa's in winter (March 2021)